We have a proven track record in providing quality service with a focus on heavy civil, mechanical, and infrastructure scope requirements. We have executed work on large mill process and material handling systems. We have constructed water treatment plants, acid plants, oxygen plants, steel and concrete tanks, earth dykes, roads, HVAC systems, and completed process facilities and maintenance shut downs. We also specialize in supplying a skilled workforce for operations and maintenance support in operating facilities.
The Gunnar Mine project involved construction of an engineered cover system over waste rock piles; Construction of two landfill(s) (“Landfill A -Non Hazardous” and “Landfill B – Hazardous”);Legacy Waste cleanup within the historical mine boundaries; Consolidation, treatment and disposal of PHC soils and rock; Consolidation, screening, amendment treatment and disposal of sulphur contaminated soils and rock; excavation, and re-establishment of a historical drainage channel reducing contamination loading of water percolating through the waste rock piles; construction of 8km of haul roads, construction and installation of three (3) stainless steel engineered mine opening caps; and construction of an cover over the general site.
QM Points was contracted to perform the reclamation and remediation of the former Newcor Mine site. Newcor mine was a former underground gold mine located on the shore of Douglas Lake, SK with historical Arsenic contamination. The project consisted of road repair, clearing and grubbing of vegetation, placement of rip rap over historical Arsenic contamination on the shoreline and within the water of Douglas Lake, consolidation of approximately 3,400m3 of former tailings and contaminated soil into 3 landforms, construction of an engineered cover system for the landforms, construction of an engineered concrete and steel cover for the former mineshaft entrance, topsoil placement and re-seeding of the worksite
The scope of this project included civil earthworks, HDPE liner installation, HDPE pipe fusion, demolition, structural steel, pressure welded pipe installation, concrete foundations, pump installation, and commissioning. The project was completed on time and within the budget for March Consulting.
The scope of work of this project includes the installation, inspection and removing of the scaffolds as per the drawings.
The scope of this project included excavation, trenching and backfilling, the installation and fusion of HDPE pipe, installing heat trace systems, and the installation of stairs and a canopy.
Whether a project calls for labourers, carpenters, pipefitters, welders, or operators, we supply a variety of skilled workers as needed to complete the job.
Points Athabasca manages the maintenance of the 184km Athabasca Seasonal Road from Points North to Stony Rapids / Black Lake, approximately 84km of overland / ice roads from Stony Rapids to Fond du Lac and approximately 100km of ice roads from Fond du Lac to Uranium City.
Scope of work included clearing and grubbing for freeze pad expansion and utility corridor using a fleet of excavators and articulated rock trucks. The project was completed ahead of schedule and received an excellent rating from Cameco’s Construction Management Team.
Scope of work included installation of new compressors and associated piping, pump foundations, tank replacement and pump installations. Work was completed on surface and underground.
Scope of work included topsoil removal, sub-base construction and compaction, gravel installation, fencing, concrete foundation and screwpiles. Project was completed on schedule and on budget in 2015, with an excellent rating from SaskPower’s Supplier Performance Management system
Points Athabasca was hired for the installation and commissioning of process piping and pumping systems to support Cameco’s mining methods and operations at the Cigar Lake mine. All pressure piping was completed under a quality control process and passes all requirements of client and provincial specifications. This project employed 125 people with an average of 30% from the local communities and region.